Getting Ready for the Basement Slab

Project: Lee High Rd, SE13

Works are progressing well at our Lee High Rd project in Lewisham to provide seventeen new apartments and two commercial units. Demolition is complete, pile foundations have been installed and the first phase of bulk excavations has started. Now it is time to install pile caps, drainage and lift pits before fixing reinforcement steel and pouring concrete for the basement of the reinforced concrete frame. This will make up the basement, ground and first floors of the development and it will contain the two commercial units, disabled parking spaces and entrance to apartments. All carried out surrounded by red routes, restricted roads, party walls and a river.